Aqua Water Treatment Facilities
Location
Pennsylvania Sites
Project Facts
2014 – Current
$1.2M
Multiple Sites
Owner
Aqua Water Company
Delivery Method
Design-Bid-Build
Project Description
Project consisted retrofit of existing 5KV switchgear and five 2 MW CAT generators. Complete integration of a custom Hot Back Up PLC system in a Master Control Panel to control the entire water treatment plant for emergency standby power and split bus peak shaving and curtailment.